Contract
No: HK/2015/01 Wanchai Development Phase II and Central Wanchai
Bypass Sampling, Field Measurement and
Testing Work (Stage 3) Environmental
Permit no. EP-356/2009, Further
Evironmental permit nos. fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 Fep-06/356/2009, FEP-07/356/2009 and
FEP-08/356/2009 Quarterly Environmental Monitoring
and Audit Report
- December 2017 to February
2018 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics
Limited 11/F Centre
Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
27 March
2018 |
2.2 Scope of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
2.5 Principal Work and Activities
5.5. Review of the Reasons for and the Implications of
Non-compliance
5.6. Summary of action taken in the event of and follow-up
on non-compliance
6. Complaints, Notification of Summons
and Prosecution
7. Cumulative
Construction Impact due to the Concurrent Projects
lIST
OF TABLES
Table II Principal Work
Activities for Contract no. HK/2009/02
Table IV Principal Work
Activities for Contract no. HY/2009/19
Table V Principal Work
Activities for Contract no. HK/2012/08
Table VI Principal Work Activities for Contract no. HY/2010/08
Table 2.1 Schedule 2 Designated
Projects under this Project
Table 2.2 Details of Individual
Contracts under the Project
Table 2.3 Contact Details of
Key Personnel
Table 2.5 Principal Work Activities for Contract no. HK/2009/02
Table 2.7 Principal Work
Activities for Contract no. HY/2009/19
Table 2.8 Principal Work Activities for Contract no. HK/2012/08
Table 2.9 Principal Work Activities for Contract no. HY/2010/08
Table 3.1 Noise Monitoring Stations
Table 3.2 Air Monitoring
Stations
Table 3.3 Marine Water Quality
Stations for Water Quality Monitoring
Table 3.4 Marine Water Quality
Monitoring Frequency and Parameters
Table
3.5 Marine Water Quality Stations for Enhanced Water
Quality Monitoring
Table 4.1 Noise Monitoring Station for Contract nos. HK/2009/02
Table 4.3 Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.4 Noise Monitoring Stations for Contract no. HY/2010/08
Table 4.6 Air Monitoring Station for Contract no. HK/2009/02
Table 4.8 Air Monitoring Stations for Contract no. HY/2009/19
Table 4.9 Air Monitoring Station
for Contract no. HK/2012/08
Table 4.10 Air Monitoring Stations for Contract no. HY/2010/08
Table 4.12 Water Monitoring Stations for
Contract no. HK/2009/02
Table 4.13 Water Monitoring Stations for Contract no. HK/2012/08
Table 4.16 Water quality monitoring Stations for Contract no. HY/2010/08
Table 4.17 Enhance Dissolved
Oxygen Monitoring Stations for Contract no. HY/2010/08
Table 4.18 Details of Waste
Disposal for Contract no. HK/2009/01
Table 4.19 Details of Waste
Disposal for Contract no. HK/2009/02
Table 4.20 Details
of Waste Disposal for Contract no. HY/2009/15
Table 4.21 Details of Waste Disposal for Contract no. HY/2009/19
Table 4.22 Details of
Waste Disposal for Contract no. HK/2012/08
Table 4.23 Details of Waste Disposal for
Contract no. HY/2010/08
Table 6.1 Cumulative Statistics
on Complaints
Table 6.2 Cumulative Statistics
on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 3.1 Locations of Environmental
Monitoring Stations
lIST OF APPENDIces
Appendix 2.1 Environmental Mitigation Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix
4.1 Noise Monitoring
Graphical Presentations
Appendix
4.2 Air Quality Monitoring
Graphical Presentations
Appendix
4.3 Water Quality Monitoring
Graphical Presentations
Appendix 5.1 Event Action Plans
Appendix 6.1 Complaint Log
Appendix 7.1 Construction Programme of
Individual Contracts
Construction Activities for the
Reported Period
Table II Principal Work Activities for Contract no.
HK/2009/02
December 2017 |
January 2018 |
February 2018 |
Nil |
Nil |
Nil |
Table IV Principal Work Activities for Contract no. HY/2009/19
December 2017 |
January 2018 |
February 2018 |
Nil |
Nil |
Nil |
Table V Principal Work Activities for Contract no.
HK/2012/08
December 2017 |
January 2018 |
February 2018 |
Trimming of rock level |
Trimming of rock level |
Trimming of rock level |
Table VI
Principal Work Activities for Contract
no. HY/2010/08
December 2017 |
January 2018 |
February 2018 |
Diversion pipe maintenance Diaphragm Wall Removal Works Removal of reclamation at TS3E and
TS3W |
Diversion pipe maintenance Diaphragm Wall Removal Works Removal of reclamation at TS3E and
TS3W |
Diversion pipe maintenance Seawall reinstatement |
Noise Monitoring
Air Quality Monitoring
Water Quality Monitoring
Complaints, Notifications of
Summons and Successful Prosecutions
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-356/2009 and Further Environmental
permit nos. FEP-02/356/2009,
FEP-03/356/2009,
FEP-04/356/2009, FEP-06/356/2009, FEP-07/356/2009 and FEP-08/356/2009 to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved
EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link
(Register No. AEIAR-041/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.4 of EM&A Manual and “Environmental
Monitoring and Audit Requirements” under Particular
Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
during the period from 27th December 2017
to 26th February 2017.
Section 1 Introduction – details the scope and structure of the
report.
Section 2 Project Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Monitoring Requirements – summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4 Monitoring Results – summarizes the monitoring results
obtained in the reporting period.
Section 5 Compliance Audit – summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 6 Complaints,
Notification of summons and Prosecution – summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai
Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern
Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved
on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested east-west Connaught Road Central/Harcourt Road / Gloucester Road
Corridor (the Corridor) which is currently operating beyond its capacity. The
CWB will provide relief to the existing congestion along the Corridor and cater
for the anticipated growth of traffic on Hong Kong Island. Without the CWB and
its access roads, there will not be sufficient capacity to serve the heavy
traffic demands at both strategic and local levels.
2.2.1.
The
Project is located mainly in Wan Chai North, Causeway Bay and North Point, and
is demarcated by Gloucester Road and Victoria Park Road to the south, Fenwick
Pier Street to the west and Tong Shui Road Interchange to the east, as shown in
Figure 2.1.
2.2.2.
The
study area encompasses existing developments along the Wan Chai, Causeway Bay
and North Point shorelines. Major land uses include the Hong Kong Convention
& Exhibition Centre (HKCEC) Extension, the Wan Chai Ferry Pier, the ex-Wan
Chai Public Cargo Working Area (ex-PCWA), the Royal Hong Kong Yacht Club (RHKYC),
the Police Officers' Club, the Causeway Bay Typhoon Shelter (CBTS) and
commercial and residential developments.
2.2.3.
The scope of the Project comprises:
·
Land formation for key transport infrastructure and
facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for
connection to the Trunk Road and for through traffic from Central to Wan Chai and
Causeway Bay. The land formed for the above transport infrastructure will provide
opportunities for the development of an attractive waterfront promenade for the
enjoyment of the public
·
Reprovisioning / protection of the existing
facilities and structures affected by the land formation works mentioned above
·
Extension, modification, reprovisioning or
protection of existing storm water drainage outfalls, sewerage outfalls and
watermains affected by the revised land use and land formation works mentioned
above
·
Upgrading of hinterland storm water drainage system
and sewerage system, which would be rendered insufficient by the land formation
works mentioned above
·
Provision of the ground level roads, flyovers,
footbridges, necessary transport facilities and the associated utility services
·
Construction of the new waterfront promenade,
landscape works and the associated utility services
·
The Trunk Road (i.e. CWB) within the study area and
the associated slip roads for connection to the Trunk Road.
2.2.4.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HK/2010/06 – Wan Chai
Development Phase II – Central – Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-05/356/2009
2.3.2
The construction works were completed and the FEP-05/356/2009 was
surrendered by the Contractor on 3 October 2014.
Contract no. HY/2009/11 – Wan Chai
Development Phase II – Central – Wan Chai Bypass - North Point Reclamation
2.3.3
The construction works were completed and the FEP-01/356/2009 was
surrendered by the Contractor on 22 October 2012.
2.3.4
Due to the multi-contract nature of the Project, there are a
number of contracts sub-dividing the whole works area into different work areas
to be commenced. Contractors of
individual contracts will be required by the EP holder to apply Further
Environmental Permits (FEP) such that the impact monitoring stations are
sub-divided accordingly to facilitate the implementation of EM&A programme
and to streamline the EM&A reporting for individual FEP holders
correspondingly.
2.3.5
The details of individual contracts are summarized in Table2.2.
Table
2.2 Details of Individual Contracts
under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II – Central –Wanchai Bypass at Hong Kong
Convention and Exhibition Centre |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central – Wan Chai Bypass – North
Point Reclamation |
DP3 |
17 March 2010 (Completed) |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 (Completed) |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 (Completed) |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
10 March 2014 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2012/08 |
Wan Chai
Development Phase II Central- Wan Chai Bypass at
Wan Chai West |
DP1,DP2,
DP3 |
5 March 2013 |
HY/2011/08 |
Central-Wan Chai
Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning |
DP1 |
8 October 2014 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer’s Representative for
WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3010 |
|
Chun Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project
Manager |
Mr. Simon Liu |
9304 8355 |
2587 1878 |
Environmental
Officer |
Mr. Terry
Tsang |
6683 9394 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project
Manager |
Mr. Paul Yu |
3658 3085 |
2827 9996 |
Quality & Environmental Manager |
Mr. C.P. Ho |
9191 8856 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. Chris Leung |
3557 6393 |
2566 2192 |
Site Agent |
Mr. Patrick Ho |
3557 6405 |
|||
Construction Manager |
Mr. Tom Tong |
3557 6415 |
|||
Environmental Officer |
Mr. Desmond Ho |
3557 6347 |
|||
Environmental Supervisor |
Mr. Gordon Lai |
6145 6365 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Site Agent |
Mr. David Lau |
3758 8879 |
2570 8013 |
Deputy Site Agent |
Mr. Andy Chan |
9879 4325 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction
Manager (Marine) |
Mr. Wingo Wong |
9608 6366 |
|||
Construction Manager (Land) |
Mr. Ray Ho |
9834 1010 |
|||
Construction Manager (Land) |
Mr. Yung Kwok Wah |
9834 1010 |
|||
Construction Manager
(Ext. Works) |
Mr. Paul Wan |
6629 4652 |
|||
Construction Manager (Approach Ramp
Phase 1) |
Mr. Billy Lam |
9288 0405 |
|||
China State- Build King Joint Venture |
Contractor under Contract no. HK/2012/08 |
Project Director |
Mr. C. N. Lai |
9106 5806 |
2877 1522 |
Project Manager |
Mr. George Cheung |
9268 1918 |
|
||
Environmental Officer |
James Ma |
9130 9549 |
|
||
Environmental Supervisor |
Mr. Y. L. Ho |
9856 5669 |
|
||
China State |
Contractor under
Contract no. HY/2010/08 |
Project Director |
Mr. Chris Leung |
3467 4299 |
2566 8061 |
Project Manager |
Mr. Chan Ying Lun |
3418 3001 |
|
||
Site Agent |
Mr. Thomas Lui |
3557 6452 |
|
||
Marine Manager |
Mr. Nickael Chan |
3557 6333 |
|
||
Construction Manager |
Mr. Tom Tong |
3557 6415 |
|
||
Environmental Officer |
Mr. Gabriel Wong |
3557 6466 |
|
||
Ramboll Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.5.1.
During
this reporting period, the principal work activities for Contract no.
HK/2009/02 are summarized in Table 2.5.
Table
2.5 Principal Work Activities for Contract no.
HK/2009/02
December
2017 |
January 2018 |
February
2018 |
Nil |
Nil |
Nil |
2.5.2.
Contract no. HY/2009/19 was commenced on 24 March
2011. During this reporting period, the principal work activities for Contract
no. HY/2009/19 are summarized as below:
Table
2.7 Principal Work Activities for Contract no. HY/2009/19
December
2017 |
January 2018 |
February
2018 |
Nil |
Nil |
Nil |
2.5.3.
Contract no. HK/2012/08 was commenced on March 2013.
During this reporting period, the principal work activities for Contract no. HK/2012/08
are summarized as below:
Table
2.8 Principal Work Activities for Contract no. HK/2012/08
December
2017 |
January 2018 |
February
2018 |
Trimming of rock level |
Trimming of rock level |
Trimming of rock level |
2.5.4.
Contract no. HY/2010/08 was commenced on 21 March
2013. During this reporting period, the principal work activities for Contract
no. HY/2010/08 are summarized as below:
Table 2.9 Principal Work Activities for Contract no.
HY/2010/08
December
2017 |
January 2018 |
February
2018 |
Diversion pipe maintenance
Diaphragm Wall Removal Works
Removal of reclamation at TS3E and TS3W |
Diversion pipe maintenance
Diaphragm Wall Removal Works
Removal of reclamation at TS3E and TS3W |
Diversion pipe maintenance
Seawall reinstatement |
2.5.5.
Implementation
status of the recommended mitigation measures during this reporting period is
presented in Appendix 2.1.
Noise Monitoring Stations
3.1.1. The noise monitoring stations for the Project
are listed and shown in Table 3.1 and Figure 3.1. Appendix 3.1 shows the established Action/Limit Levels
for the monitoring works.
Table
3.1 Noise Monitoring Stations
Station |
Description |
M1a |
Footbridge at Ex-Harbour Road Sports Centre* |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire
Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church
Henrietta Secondary School |
Remarks*: With respect to
the demolition of Ex-harbour Road Sports Centre, the respective noise
monitoring station M1a- Harbour Road Sports Centre were finely adjusted on 16
and 25 May 2017 and thereafter to the Footbridge at Harbour Road Sports Centre
for noise monitoring.
Noise Monitoring
Parameters, Frequency and Duration
3.1.2. The construction noise level
shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq).
Leq (30 minutes) shall be used as the monitoring parameter for the
time period
between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq
(5 minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
3.1.3. Noise monitoring shall be
carried out at all the designated monitoring stations. The monitoring frequency
shall depend on the scale of the construction activities. The following is an
initial guide on the
regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
·
one
set of measurements between 0700 and 1900 hours on normal weekdays.
3.1.4. If construction works are extended to include works
during the hours of 1900 – 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
3.1.5. Real time noise shall be carried out at the
designated monitoring stations. The following is an initial guide on the
regular monitoring frequency for each station on a 24 hours daily basis when
noise generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
·
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
·
One
set of measurements between 2300 and 0700 hours on next day on everyday.
Monitoring Equipment
3.1.6. As referred
to in the Technical Memorandum ™ issued under the NCO, sound level meters in
compliance with the International Electrotechnical Commission Publications 651:
1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying
out the noise monitoring. Immediately prior to and following each noise
measurement the accuracy of the sound level meter shall be checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
3.1.7. Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
Air Quality Monitoring
Stations
3.2.1.
The
air monitoring stations for the Project are listed and shown in Table
3.2 and Figure 3.1. Appendix 3.1 shows the established Action/Limit Levels for the
monitoring works.
Table 3.2 Air Monitoring Stations
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Site
Office** |
North Point |
CMA2a |
Causeway Bay Community
Centre |
Causeway Bay |
CMA3a |
CWB PRE Site Office * |
Causeway Bay |
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5b |
Pedestrian Plaza*** |
Wan Chai |
CMA6a |
WDII PRE Site Office * |
Wan Chai |
Remarks*: As per the ENPC
meeting in January 2011, the monitoring stations CMA3a - Future CWB site office
at Wanchai Waterfront Promenade and CMA6a - Future AECOM site office at Work
Area were renamed as remark.
Remarks**: The location ID of monitoring station
CMA1b was updated as “Oil Street Site Office” in April 2013.
Remarks***:
The station ID and monitoring location was updated in December 2014 with
respect to monitoring station relocation.
Air Monitoring Parameters,
Frequency and Duration
3.2.2.
One-hour
and 24-hour TSP levels should be measured to indicate the impacts of
construction dust on air quality. The 24-hour TSP levels shall be measured by
following the standard high volume sampling method as set out in the Title 40
of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.
3.2.3.
All
relevant data including temperature, pressure, weather conditions, elapsed-time
meter reading for the start and stop of the sampler, identification and weight
of the filter paper, and any other local atmospheric factors affecting or
affected by site conditions, etc., shall be recorded down in detail.
3.2.4.
For
regular impact monitoring, the sampling frequency of at least once in every
six-days, shall be strictly observed at all the monitoring stations for 24-hour
TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least
three times in every six-days should be undertaken when the highest dust impact
occurs.
Sampling Procedure and
Monitoring Equipment
3.2.5 High
volume samplers (HVSs) in compliance with the following specifications shall be
used for carrying out the 1-hour and 24-hour TSP monitoring:
·
0.6
- 1.7 m3 per minute adjustable flow range;
·
equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
·
installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
capable
of providing a minimum exposed area of 406 cm2;
·
flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
equipped
with a shelter to protect the filter and sampler;
·
incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
equipped
with a flow recorder for continuous monitoring;
·
provided
with a peaked roof inlet;
·
incorporated
with a manometer;
·
able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
easily
changeable filter; and
·
capable
of operating continuously for a 24-hour period.
3.2.6 Initial
calibration of dust monitoring equipment shall be conducted upon installation
and thereafter at bi-monthly intervals. The transfer standard shall be
traceable to the internationally recognized primary standard and be calibrated
annually. The concern parties such as IEC shall properly document the
calibration data for future reference. All the data should be converted into
standard temperature and pressure condition.
Laboratory Measurement /
Analysis
3.2.7 A clean
laboratory with constant temperature and humidity control, and equipped with
necessary measuring and conditioning instruments to handle the dust samples
collected, shall be available for sample analysis, and equipment calibration
and maintenance. The laboratory should be HOKLAS accredited.
3.2.8 An
alternative non-HOKLAS
accredited laboratory was set-up for carrying out the laboratory
analysis, the laboratory equipment was approved by the ER on 8
February 2011 and
the measurement procedures were witnessed by the IEC. Any measurement performed by
the laboratory was be demonstrated to the satisfaction of the ER and IEC. IEC shall
regularly audit to the measurement performed by the laboratory to ensure the
accuracy of measurement results.
3.2.9 Filter
paper of size 8" x 10" shall be labelled before sampling. It shall be
a clean filter paper with no pinholes, and shall be conditioned in a
humidity-controlled chamber for over 24-hours and be pre-weighed before use for
the sampling.
3.2.10 After
sampling, the filter paper loaded with dust shall be kept in a clean and
tightly sealed plastic bag. The filter paper shall then be returned to the
laboratory for reconditioning in the humidity controlled chamber followed by
accurate weighing by an electronic balance with readout down to 0.1 mg. The
balance shall be regularly calibrated against a traceable standard.
3.2.11 All the
collected samples shall be kept in a good condition for 6 months before
disposal.
impact monitoring for
odour patrol
3.2.12 Odour patrols along the
shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai Public Cargo Working
Area when there is temporary reclamation in Causeway Bay Typhoon Shelter and/or in the ex-Wan Chai Public Cargo
Working Area, or when there is dredging of the odorous sediment and slime at
the south-western corner of the Causeway Bay Typhoon Shelter. Odour patrols
will be carried out at bi-weekly intervals during July, August and September by
a qualified person of the ET who shall:
·
be
at least 16 years of age;
·
be
free from any respiratory illnesses; and
·
not
be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30
min
·
before
and during odour patrol
3.2.13 Odour patrol shall be conducted by independent
trained personnel / competent persons patrolling and sniffing around the shore
as shown in Figure 3.1 to detect any odour at
the concerned hours (afternoon is preferred for higher daily temperature).
3.2.14 The qualified person will use the nose (olfactory
sensor) to sniff odours at different locations. The main odour emission sources
and the areas to be affected by the odour nuisance will be identified.
3.2.15 The perceived odour intensity is to be divided into
5 levels which are ranked in the descending order as follows:
·
0 -
Not detected. No odour perceived or an odour so weak that it cannot be easily
characterized or described;
·
1 -
Slight Identifiable odour, and slight chance to have odour nuisance;
·
2 -
Moderate Identifiable odour, and moderate chance to have odour nuisance;
·
3 -
Strong Identifiable, likely to have odour nuisance;
·
4 -
Extreme Severe odour, and unacceptable odour level.
3.2.16 The findings including odour intensity, odour
nature and possible odour sources, and also the local wind speed and direction
at each location will be recorded. In addition, some relevant meteorological
and tidal data such as daily average temperature, and daily average humidity,
on that surveyed day will be obtained from the Hong Kong Observatory Station
for reference. The Action and Limit levels for odour patrol are shown in Appendix 3.1.
3.3.1. The EIA Report has identified that the key water
quality impact would be associated with the dredging works during the
construction phase. Marine water quality
monitoring for dissolved oxygen (DO), suspended solid (SS) and turbidity is
therefore recommended to be carried out at selected WSD flushing water
intakes. The impact monitoring should be
carried out during the proposed dredging works to ensure the compliance with
the water quality standards.
3.3.2. The
updated EM&A Manual for EP-356/2009 (Version in March 2011) is approval by
EPD on 29 April 2011. As such, the Action Level and Limit Level for the wet
season (April – September) will be effected and applied to the water quality
monitoring data from 30 April 2011.
Water Quality Monitoring Stations
3.3.3. Water quality monitoring was undertaken at WSD salt
water intakes and cooling water intakes along the seafront of the Victoria
Harbour. The proposed water quality
monitoring stations of the Project are shown in Table 3.3 and Figure 3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table
3.3
Marine Water Quality Stations for Water
Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C7 |
Windsor House |
837193.7 |
816150.0 |
P1 |
HKCEC
Phase I |
835774.7 |
816179.4 |
P3 |
The Academy of performing Arts |
835824.6 |
816212.0 |
P4 |
Shui on Centre |
835865.6 |
816220.0 |
P5 |
Government
Buildings (Wanchai
Tower / Revenue Tower / Immigration Tower) |
835895.2 |
816215.2 |
Cooling Water Intake / WSD Salt Water Intake |
|||
RW21-P789 |
Great
Eagle Centre/ Sun Hung Kai Centre/ WSD Wanchai salt water intake |
836268.0 |
816020.0 |
Remarks: - The cessation of seawater intake
operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was
then terminated since 17 May 2011.
-
4-week post construction water quality
monitoring at WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012
and the water quality monitoring at WSD 10 and WSD15 were temporary suspended
since 8 Feb 2012, and WSD9 and WSD17 was implemented with respect to HK/2009/02
from 8 Feb 2012 onwards.
-
C8 and C9 were
implemented with respect to HY/2009/19 from 28 Jan 2012.
-
C8 & C9 were
temporary suspended since 30 March 2013.
-
WSD7 and WSD20 water
quality monitoring were temporarily suspended from 27 Apr 2012.
-
C2, C3 C4e and C4w
water quality monitoring station was temporarily suspended since 24 Apr 2013
-
C5e and C5w water
quality monitoring station was temporarily suspended since 29 July 2013.
-
WSD21 water quality
monitoring station was temporarily suspended since 12 Mar 2014
-
WSD9 and WSD17 water
quality monitoring station was temporarily suspended since 8 Sep 2014 flood
tide.
-
The water quality monitoring station C1 shall
be associated with Contract No. HK/2009/02 upon commencement of marine works
under DP3 at WCR3 area
-
The water quality monitoring station RW21-P789
was adjusted to RW21-P789E and RW21-P789W since 28 November 2016 ebb-tide.
-
The water quality monitoring was reverted to
previous monitoring station RW21-P789 from PW21-P789E and RW21-P789W from 25
January 2017 onwards.
Water Quality Parameters
and frequency
3.3.4. Monitoring of dissolved oxygen (DO), turbidity and
suspended solids (SS) shall be carried out at WSD flushing water intakes and
cooling water intakes. DO and Turbidity are measured in-situ while SS is
determined in laboratory.
3.3.5. In association with the water quality parameters,
other relevant data shall also be measured, such as monitoring
location/position, time, sampling depth, water temperature, pH, salinity,
dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal
stage, and any special phenomena and work underway at the construction site
etc.
3.3.6. The interval between two sets of monitoring should
not be less than 36 hours except where there are exceedances of Action and/or
Limit Levels, in which case the monitoring frequency will be increased. Table 3.4 shows the proposed
monitoring frequency and water quality parameters. Duplicate in-situ measurements and water
sampling should be carried out in each sampling event. For selection of tides for in-situ measurement
and water sampling, tidal range of individual flood and ebb tides should be not
less than 0.5m.
Table
3.4 Marine Water Quality Monitoring Frequency
and Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week
baseline monitoring period |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
During marine construction works |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
After completion of marine construction works |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1. For
selection of tides for in-situ measurement and water sampling, tidal range of
individual flood and ebb tides should be not less than 0.5m.
2.
Turbidity should be
measured in situ whereas SS should be determined by laboratory.
Dissolved Oxygen and
Temperature Measuring Equipment
3.3.7. The instrument should be a portable, weatherproof
dissolved oxygen measuring instrument complete with cable, sensor,
comprehensive operation manuals, and use a DC power source. It should be
capable of measuring:
·
a
dissolved oxygen level in the range of 0-20 mg/l and 0-200% saturation
·
a
temperature of 0-45 degree Celsius
3.3.8. It should have a membrane electrode with automatic
temperature compensation complete with a cable. Sufficient stocks of spare
electrodes and cables should be available for replacement where necessary.
(e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with
reel and cable or an approved similar instrument).
3.3.9. Should salinity compensation not be build-in in the
DO equipment, in-situ salinity shall be measured to calibrate the DO equipment
prior to each DO measurement.
Turbidity Measurement
Instrument
3.3.10 The
instrument should be a portable, weatherproof turbidity-measuring instrument
complete with comprehensive operation manual. The equipment should use a DC
power source. It should have a photoelectric sensor capable of measuring
turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach
model 2100P or an approved similar instrument).
Sampler
3.3.11 Water sampler comprises a transparent PVC
cylinder, with a capacity of not less than 2 litres, and can be effectively
sealed with latex cups at both ends. The sampler should have a positive
latching system to keep it open and prevent premature closure until released by
a messenger when the sampler is at the selected water depth (e.g. Kahlsico
Water Sampler or an approved similar instrument).
Sample Container and
Storage
3.3.12 Water
samples for suspended solids measurement should be collected in high-density
polythene bottles, packed in ice (cooled to 4°C without being frozen), and
delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection
for analysis.
Water Depth Detector
3.3.13 A
portable, battery-operated echo sounder shall be used for the determination of
water depth at each designated monitoring station. This unit can either be
handheld or affixed to the bottom of the workboat, if the same vessel is to be
used throughout the monitoring programme.
Salinity
3.3.14 A portable
salinometer capable of measuring salinity in the range of 0-40 ppt shall be
provided for measuring salinity of the water at each of monitoring location.
Monitoring Position
Equipment
3.3.15 A
hand-held or boat-fixed type digital Global Positioning System (GPS) with
waypoint bearing indication or other equivalent instrument of similar accuracy
shall be provided and used during monitoring to ensure the monitoring vessel is
at the correct location before taking measurements.
Calibration of In-situ
Instruments
3.3.16 All
in-situ monitoring instrument shall be checked, calibrated and certified by a
laboratory accredited under HOKLAS or equivalent before use, and subsequently
re-calibrated at 3 monthly intervals throughout all stages of the water quality
monitoring. Responses of sensors and electrodes should be checked with
certified standard solutions before each use. Wet bulb calibration for a DO
meter shall be carried out before measurement at each monitoring location.
3.3.17 For the on
site calibration of field equipment by the ET, the BS 127:1993, "Guide to
Field and on-site test methods for the analysis of waters" should be
observed.
3.3.18 Sufficient
stocks of spare parts should be maintained for replacements when necessary.
Backup monitoring equipment shall also be made available so that monitoring can
proceed uninterrupted even when some equipment is under maintenance, calibration,
etc.
Laboratory Measurement /
Analysis
3.3.19 Analysis
of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS
Technichem (HK) Pty Ltd. Water samples of about 1L shall be collected at the
monitoring stations for carrying out the laboratory SS determination. The SS
determination work shall start within 24 hours after collection of the water
samples. The SS determination shall follow APHA 19ed or equivalent methods
subject to the approval of IEC and EPD.
Enhanced Water Quality Monitoring
in the ex-Wan Chai Public Cargo
Working Area and the
Causeway Bay Typhoon Shelter
3.3.20 The
enhanced water quality monitoring and audit programme is to avoid aggravation
of odour nuisance from seawater arising from temporary reclamation in the
ex-Wan Chai Public Cargo Working Area and the Causeway Bay Typhoon Shelter.
3.3.21 Dissolved
oxygen monitoring at the intakes C6 and C7 in Causeway Bay Typhoon Shelter when
there is temporary reclamation in Causeway Bay Typhoon Shelter and at the
south-western and south-eastern corners of the ex-Wan Chai Public Cargo Working
Area. The proposed water quality monitoring stations of the Project are shown
in Table
3.5 and Figure 3.1.
Table 3.5 Marine
Water Quality Stations for Enhanced Water Quality Monitoring
Station |
Location |
C6 |
Excelsior Hotel |
C7 |
Windsor House |
Ex-WPCWA-SW |
South-western of the ex-Wan Chai
Public Cargo Working Area |
Ex-WPCWA-SE |
South-eastern of the ex-Wan Chai
Public Cargo Working Area |
Remarks:
1.
Enhanced DO monitoring at Windsor House Cooling
(Station Ref: C7) was temporarily suspended since 22 October 2014 with respect
to the formation of temporary reclamation zone TS3 and was resumed from 1
February 2018 onward with respect to the completion of removal of temporary
reclamation zone.
2.
Enhanced DO monitoring at Monitoring station at
Ex-WPCWA SE was temporarily suspended from 31 August 2015 with respect to
seawall reinstatement works and formation of active works area. The Enhance DO
monitoring at Ex-WPCWA SE was resumed on 11 May 2016 due to completed section
of seawall reinstatement works are Ex-PCWA.
3.3.22 The
monitoring of dissolved oxygen are to be carried out 3 days per week, at
mid-flood and mid-ebb tides for 3 water depths (1m below water surface,
mid-depth and 1m above sea bed, except where the water depth less than 6m, the
mid-depth may be omitted. If the water depth be less than 3m, only the
mid-depth will be monitored).
Daily SS Monitoring and 24
hours Turbidity Monitoring System
3.3.23 During
dredging of the sediment at the south-western corner of the Causeway Bay
Typhoon Shelter, daily monitoring of suspended solids and 24 hour monitoring of
turbidity at the cooling water intakes (C6 and C7) shall be conducted.
3.3.24 The 24
hours monitoring of turbidty at the cooling water intakes (C6 and C7) shall be
established by setting up a continuous water quality monitoring station in
front of the intakes during the dredging activities. The monitoring system include the turbidity
sensor and data logger which is capable of data capturing at every 5 minutes.
The data shall be downloaded daily and compared with the Action and Limit level
determined during the baseline water qualtiy monitoring at the cooling water
intake locations.
Additional Dissovled
oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW
3.3.25 In
response to the Condition 2.18 of the Environmental Permit no. EP-356/2009
requiring that a silt curtain / impermeable barrier system be installed to
channel water discharge flow from Culvert L to locations outside the embayment
area, a proposed replacement of the requirement with additional dissolved
oxygen monitoring has been conducted at three monitoring stations, namely A, B
and C between the eastern seawall of Central Reclamation Phase III and the
HKCEC Extension since November 2011 under EP-356/2009 so that DO level between
the eastern seawall of Central Reclamation Phase II and the HKCEC extension
could be continuously monitored.
3.3.26 With
respect to the commencement of dredging works under HK/2012/08 and the
installation of MTR precast protection unit, the enhanced water quality
monitoring for Culvert L was temporarily suspended since 24 July 2013
3.3.27 The
monitoring of dissolved oxygen are to be carried out once per week, at
mid-flood and mid-ebb tides for 3 water depths (1m below water surface,
mid-depth and 1m above sea bed, except where the water depth less than 6m, the
mid-depth may be omitted. If the water depth be equal to or less than 3m, only
the mid-depth will be monitored).
4.0.1. The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various
contracts, latest status of work commencement and monitoring stations is shown
in
Figure
2.1 and Figure
3.1. The monitoring results are presented in according to the
Individual Contract(s).
4.0.2. According to
EP-364/2009/A Part B, “Scale and Scope of Designated Project”, Remarks (c),”The
permanent and temporary reclamation and associated dredging works related to
the CWB construction are separately covered by environmental permit No.
EP-356/2009 issued to Civil Engineering and Development Department”, and
marine piling works to be conducted by the Contractor of Contract no. HY/2009/19
from 28 January 2012 was considered to be governed under EP-356/2009. As the
construction site area of Contract no. HY/2009/11 had already been handed over
to Contract no. HY/2009/19, the designated noise, water and air quality
monitoring stations for Contract no. HY/2009/11 would be shared with Contract
no. HY/2009/19 from 28 January 2012.
4.0.3. As confirmed by WDII RSS, the marine
construction works under Contract HK/2009/01 have been completed since 24 July
2017, the monitoring association with Contract HK/2009/01 and relevant
reporting has been ceased from November 2017.
4.0.4. As confirmed by CWB RSS, the marine
construction works under Contract HY/2009/15 and relevant reporting have been
completed by 19 June 2017, the monitoring association with Contract HY/2009/15
and relevant reporting has been ceased from November 2017.
Contract no. HK/2009/02 - Wan Chai Development
Phase II – Central – Wan Chai Bypass at WanChai East
4.1.1.
The
proposed divisions of noise monitoring stations are summarized in Table
4.1 below.
Table 4.1 Noise Monitoring Station for Contract nos. HK/2009/02
Station |
Description |
M1a |
Footbridge at Ex-Harbour Road Sports Centre |
4.1.2.
Two limit level exceedances were recorded at M1a – Footbridge for
Harbour Road Sports Center on 04 and 11 December 2017 in the December 2017 reporting
month. After the investigation, the exceedances were concluded as non-Project
related
Backfilling and minor breaking works were conducted by Contract
HK/2009/02 around the concerned location with a few and non-continuous breaking
actions observed during measurement on 04 December 2017. Acoustic screening of
breaker tip was implemented by Contract HK/2009/02 and no noise contribution
was observed from the works. Meanwhile, non WDII-CWB excavation works and
hammering next to the monitoring station were observed as the major noise
contribution during monitoring. As such, the exceedance was considered as
non-Project related to Contract HK/2009/02. Nevertheless, the Contractor of
HK/2009/02 was reminded to maintain adequate noise mitigation measure around
the concerned location to avoid potential cumulative impact.
Backfilling and minor breaking works were conducted by Contract
HK/2009/02 around the concerned location with a few and non-continuous breaking
actions observed during measurement on 11 December 2017. Acoustic screening of
breaking tip was implemented by Contract HK/2009/02 and no noise contribution
was observed from the works. Meanwhile, non WDII-CWB excavation and continuous
breaking works immediately next to the monitoring station were observed as the
major noise contribution during monitoring. As such, the exceedance was
considered as non-Project related to Contract HK/2009/02. Nevertheless, the
Contractor of HK/2009/02 was reminded to maintain adequate noise mitigation
measure around the concerned location to avoid potential cumulative impact
4.1.3.
Three limit level exceedances were recorded at M1a – Footbridge for
Harbour Road Sports Centre on 29 December 2017, 16 and 23 January 2018 in the
January 2018 reporting month. After the investigation, the exceedances were
concluded as non-Project related.
Excavation were conducted by Contract HK/2009/02 around the concerned
location on 29 December 2017 and no noise contribution was observed from the
works. Meanwhile, non WDII-CWB excavation works immediately next to the
monitoring station were observed as the major noise contribution during
monitoring. As such, the exceedance was considered as non-Project related to
Contract HK/2009/02. Nevertheless, the Contractor of HK/2009/02 was reminded to
maintain adopt noise mitigation measure, if necessary, around the concerned
location to avoid potential cumulative impact.
Despite backfilling work by excavator was conducted by Contract
HK/2009/02 around the concerned location during the time of measurement on 16
January 2018, no major noise emanation from the works was observed during
monitoring. Meanwhile, steel frame erection and hammering were conducted by
non-WDII-CWB contractor next to the monitoring station and considered as the
major noise contribution during monitoring. As such, the exceedance was
considered as not relate to Project works under HK/2009/02. Nevertheless, the
Contractor of HK/2009/02 was reminded to maintain adopt noise mitigation
measure, if necessary, around the concerned location to avoid potential cumulative
impact.
Despite trench excavation work was conducted by Contract HK/2009/02
around the concerned location during the time of measurement on 23 January
2018, no major noise emanation from the works was observed during monitoring.
Meanwhile, breaking works by excavator mounted breaker was conducted under
non-WDII-CWB contractor next to the monitoring station and observed as the
major noise contribution during monitoring. As such, the exceedance was
considered as not relate to Project works under HK/2009/02.
4.1.4.
One limit level exceedances was recorded at M1a – Footbridge for Harbour
Road Sports Centre on 2 February 2018. After the investigation, the exceedances
were concluded as non-project related.
Despite trench excavation work was conducted by Contract HK/2009/02
around the concerned location during the time of measurement, no major noise
emanation from the works was observed during monitoring. Meanwhile, excavation
works and hammering were conducted under non-WDII-CWB contractor next to the
monitoring station and observed as the major noise contribution during
monitoring. As such, the exceedance was considered as not relate to Project
works under HK/2009/02.
Contract no. HY/2009/19 – Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
4.1.5.
Noise
quality monitoring at M4b and M5b have been implemented with respect to
HY/2009/19 since the marine bore piling work started on 28 Jan 2012.
4.1.6.
The
proposed division of noise monitoring stations for Contract no. HY/2009/19 are
summarized in Table 4.3 below:
Table 4.3
Noise Monitoring
Stations for Contract no. HY/2009/19
Station |
Description |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
4.1.1
Two Limit level exceedances were recorded at M6 – HK Baptist Church
Henrietta Secondary School on 08 and 20 December 2017 in the December 2017
reporting month and the exceedances were concluded as non-project related.
Despite installation of sign gantry, transportation of rebar and
housekeeping work were conducted under HY/2009/19 around the monitoring
location on 08 December 2017 and nearby traffic noise was observed as major
noise source during monitoring. As such, the exceedance was considered as non-project
related.
Breaking of paving surface at Pier F5 and F6 under Contract HY/2009/19
was conducted during the measurement on 20 December 2017 and breaking operation
behind the IECL noise enclosure was observed as the major noise influence
during measurement. Hence, the exceedance was considered as Project related. In
view of the adjustment of limit level on the subsequent monitoring date with
respect to the completion of school examination, no further exceedance was
recorded during additional monitoring conducted on 21 December 2017 at the
concerned location. Nevertheless, the Contractor of HY/2009/19 was advised to
adopt additional noise mitigation measure for future breaking works, if any, at
the concerned location during examination period, such as provision of
localized movable noise barrier to ensure that the nearby noise sensitive
receiver would not be adversely affected.
4.1.2
No action or limit level exceedance was recorded in the January 2018 reporting
month.
4.1.3
No action or limit level exceedance was recorded in the February 2018 reporting
month.
Contract
no. HY/2010/08-Central-Wanchi Bypass Tunnel (Slip Road 8 Section)
4.1.7.
The proposed division of noise monitoring
stations are summarized in Table 4.4
below.
Table 4.4 Noise Monitoring Station for Contract no. HY/2010/08
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
4.1.8.
No action or limit level exceedance was recorded in the December 2017,
January 2018 and February 2018 reporting month.
4.1.9.
All Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1.
4.2.1
1hr and 24hr TSP monitoring were conducted at CMA1b,
CMA2a, CMA3a, CMA4a, CMA5b and CMA6a in the reporting period.
Contract no. HK/2009/02 - Wan Chai Development
Phase II – Central – Wan Chai Bypass at WanChai East
4.2.2
Air
monitoring was commenced in mid-January 2011 for the land-filling work for
Contract no. HK/2009/02. The proposed division of air monitoring stations is
summarized in Table 4.6 below.
Table
4.6 Air Monitoring Station
for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
4.2.3
No action or limit exceedance was recorded in
in the December 2017, January 2018 and
February 2018 reporting month.
Contract no. HY/2009/19 –Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
4.2.4
Air monitoring at CMA1b and CMA2a have been
implemented with respect to HY/2009/19 since the marine bore piling works
started on 28 Jan 2012. No exceedance was recorded in the reporting
period.
4.2.5
The proposed division of air monitoring stations is
summarized in Table 4.8 below.
Table
4.8 Air
Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil Street Site Office |
CMA2a |
Causeway Bay Community Centre |
4.2.6
No action or limit exceedance was recorded in
in the December 2017, January 2018 and
February 2018 reporting month.
Contract no. HK/2012/08- Wan Chai Development Phase
II – Central-Wan Chai Bypass at Wan Chai West
4.2.7
The proposed division of air monitoring stations are summarized in Table
4.9 below.
Table 4.9 Air Monitoring
Stations for Contract no. HK/2012/08
Station |
Description |
CMA5b |
Pedestrian Plaza |
4.2.8
One 24hr TSP action level exceedance and one 1hr TSP limit level
exceedance were recorded at CMA5b – Pedestrian Plaza on 11 and 12 December 2017
respectively in the December 2017 reporting month.
Road and drain construction works was undertaken under Contract
HK/2012/08 around the monitoring location on 11 and 12 December 2017 and no
particular observation regarding dust emission was observed during sampling
periods. Mitigation measure including water spraying for haul road and dusty
surface were implemented by the Contractor of HK/2012/08. The exceedance was
considered not related to Project works and potentially contributed by ambient
air quality condition.
4.2.9
One 1hr TSP action level exceedance was recorded at CMA5b – Pedestrian
Plaza on 23 December 2017 in the December 2017 reporting month.
Road and drain construction works was undertaken under Contract
HK/2012/08 around the monitoring location on 23 December 2017 and no particular
observation regarding dust emission was observed during sampling periods.
Mitigation measure including water spraying for haul road and dusty surface
were implemented by the Contractor of HK/2012/08. The exceedance was considered
not related to Project works and potentially contributed by ambient air quality
condition
4.2.10
One 24hr TSP action level exceedance was recorded at CMA5b – Pedestrian
Plaza on 29 December 2017 in the January 2018 reporting month.
Road and drain construction works was undertaken under Contract
HK/2012/08 around the monitoring location on 29 December 2017 and no particular
observation regarding dust emission was observed during sampling periods.
Mitigation measure including water spraying for haul road and dusty surface
were implemented by the Contractor of HK/2012/08.One 1hr TSP action level
exceedance was recorded at CMA5b – Pedestrian Plaza on 23 December 2017.
Meanwhile, non WDII-CWB Project construction works was observed opposite to the
monitoring station on the monitoring date. In view of the above, the exceedance
was considered to be not related to the Project works under Contract HK/2012/08
and potentially contributed by ambient air quality condition and nearby traffic
exhaust. Nevertheless, the Contractor of HK/2012/08 was advised to strengthen
the overall dust suppression control measures to ensure all dusty surface and
stockpile are covered or dampened to avoid potential dust emission.
4.2.11
No action or limit level exceedance was recorded in the February 2018 reporting
month.
Contract no. HY/2010/08- Central-Wanchai Bypass
Tunnel (Slip Road 8 Section)
4.2.12
The proposed division of air monitoring stations are summarized in Table
4.10 below.
Table 4.10 Air Monitoring
Stations for Contract no. HY/2010/08
Station |
Description |
CMA3a |
CWB PRE Site Office |
4.2.13
No action or limit exceedance was recorded in
in the December 2017, January 2018 and
February 2018 reporting month.
Contract no. HK/2009/02 - Wan Chai Development Wan
Chai Development Phase II – Central – Wan Chai Bypass at WanChai East
4.3.1
Water
quality monitoring for Contract no. HK/2009/02 was commenced on 8 July 2010.
The proposed division of water monitoring stations is summarized in Table
4.12 below.
Table 4.12 Water Monitoring Stations for Contract no. HK/2009/02
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C1 |
HKCEC
Extension |
835885.6 |
816223.0 |
Cooling Water Intake |
|||
RW21-P789 |
Great Eagle Centre/ Sun Hung Kai Centre/WSD Wanchai salt
water intake / China Resources Building |
836268.0 |
816020.0 |
4.3.2
1 limit level turbidity exceedance was recorded at WQM station C1 on 19
December 2017 in the December 2017 reporting period.
No marine
construction activity was conducted on 19 December 2017. In view of no marine
construction activity was conducted during the monitoring date, the exceedance
was considered not related to Project works.
4.3.3
2 action level turbidity exceedance were recorded at WQM station
RW21-P789 on 01 and 21 December 2017 and 3 limit level turbidity exceedances were
recorded at RW21-P789 04, 19 and 23 December 2017 in the December 2017
reporting period
No marine
construction activity was conducted on 1, 4, 19, 21 and 23 December 2017. In
view of no marine construction activity was conducted during the monitoring
date, the exceedance was considered not related to Project works.
4.3.4
1 action level turbidity exceedance was recorded at WQM station
RW21-P789 on 28 December 2017 during flood tide in the January 2018 reporting
period.
No marine
construction activity under Contract HK/2009/02 was conducted on the monitoring
date, and the installed silt screen was observed generally in order. In view of
the above, it is considered that the exceedance was not related to Project
works. No exceedance was recorded in the subsequent monitoring on 30 December
2017 Flood tide.
4.3.5
1 limit level turbidity exceedance was recorded at WQM station RW21-P789
on 8 January 2018 during flood tide in the January 2018 reporting period.
No marine
construction activity under Contract HK/2009/02 was conducted on the monitoring
date, and the installed silt screen was observed generally in order. In view of
the above, it is considered that the exceedance was not related to Project
works. No exceedance was recorded in the subsequent monitoring on 10 January
2018 Flood tide.
4.3.6
No action or limit level exceedance was recorded in the February 2018
reporting period. .
Contract
no. HK/2012/08 - Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan
Chai West
4.3.7
Water
monitoring for Contract no. HK/2012/08 was commenced on 5 March 2013. The
proposed division of water monitoring stations are summarized in Table 4.13
below.
Table 4.13
Water Monitoring Stations for Contract
no. HK/2012/08
Station
Ref. |
Location |
Easting |
Northing |
|
WSD Salt Water Intake |
||||
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
|
Cooling Water Intake |
||||
P1 |
HKCEC Phase I |
835774.7 |
816179.4 |
|
P3 |
The Academy of
performing Arts |
835824.6 |
816212.0 |
|
P4 |
Shui on Centre |
835865.6 |
816220.0 |
|
P5 |
Government Buildings (Wanchai Tower /
Revenue Tower / Immigration Tower) |
835895.2 |
816215.2 |
|
4.3.8
5 action level turbidity exceedances were recorded at WQM station WSD19
on 27 November 2017, 01, 09, 12 and 23 December 2017 and 7 limit level
turbidity exceedances were recorded at WQM station WSD19 on 29 November, 01,
04, 09, 14, 19 and 21 December 2017 in the December 2017 reporting period.
Rock trimming works were conducted under Contract HK/2012/08 on 27, 29 November
and 21 December 2017 during the monitoring period and mitigation measure
including silt curtain were deployed around the works area for the above
construction works. In addition, the monitoring location was located at the
upstream location to the works area on 29 November 2017. Hence, the exceedance
were considered as non- Project related.
No marine construction activities under Contract HK/2012/08 on 01, 04, 09,
12, 14 and 23 December 2017 during the monitoring period and the exceedances were
considered not related to Project works.
4.3.9
1 limit level suspended solid exceedance was recorded at WQM station
WSD19 on 29 November 2017 in the December 2017 reporting period.
Rock trimming works were conducted under Contract HK/2012/08 on 29
November 2017 during the monitoring period and mitigation measure including
silt curtain were deployed around the works area for the above construction
works. In addition, the monitoring location was located at the upstream
location to the works area on 29 November 2017. Hence, the exceedance were
considered as non- Project related.
4.3.10
1 action level turbidity exceedances were recorded at WQM station P1 on
21 December 2017 and 1 limit level turbidity exceedance was recorded at WQM
station P1 on 19 December 2017 in the December 2017 reporting period.
No marine construction works was conducted under Contract HK/2012/08 on
19 December 2017 during the monitoring period. Hence, the exceedance was
considered as not related to the Project works under Contract HK/2012/08.
Rock trimming works were conducted under Contract HK/2012/08 on 21
December 2017during the monitoring period and mitigation measure including silt
curtain was deployed around the works area for the above construction works.
Hence, the exceedance were considered as non- Project related.
4.3.11
1 limit level turbidity exceedance was recorded at WQM station P3 on 19
December 2017 in the December 2017 reporting period.
No marine construction works was conducted under Contract HK/2012/08 on
19 December 2017during the monitoring period. Hence, the exceedance was
considered as not related to the Project works under Contract HK/2012/08.
4.3.12
1 limit level turbidity exceedance was recorded at WQM station P4 on 19
December 2017 in the December 2017 reporting period.
No marine construction works was conducted under Contract HK/2012/08 on
19 December 2017 during the monitoring period. Hence, the exceedance was
considered as not related to the Project works under Contract HK/2012/08.
4.3.13
2 action level turbidity exceedances were recorded at WQM station P5 on
01 and 21 December 2017 and 1 limit level exceedance was recorded at WQM
station P5 on 19 December 2017 in the December 2017 reporting period.
No marine construction works was conducted under Contract HK/2012/08 on
19 December 2017during the monitoring period. Hence, the exceedance was
considered as not related to the Project works under Contract HK/2012/08.
Rock trimming works were conducted under Contract HK/2012/08 on 21
December 2017 during the monitoring period and mitigation measure including
silt curtain was deployed around the works area for the above construction
works. Hence, the exceedance were considered as non- Project related.
4.3.14
4 action level turbidity exceedance was recorded at WSD19 on 28 December
2017, 30 December 2017, 8 January 2018 and 23 January 2018 during flood tide in
the January 2018 reporting period.
No marine construction activity under Contract HK/2012/08 was conducted
on 28 December 2017, 30 December 2017, 8 January 2018 and 23 January 2018
during the monitoring period. In view of above, it is considered the exceedance
was not related to Project work.
4.3.15
No action or limit level exceedance was recorded in the February 2018
reporting period.
Contract no. HY/2010/08- Central-Wanchai Bypass
Tunnel (Slip Road 8 Section)
4.3.16 The proposed division of water
quality monitoring stations are summarized in Table 4.16 and Table
4.17 below:
Table 4.16 Water quality monitoring Stations for Contract no.
HY/2010/08
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C7 |
Windsor House |
837193.7 |
816150.0 |
4.3.17 3 action level
turbidity exceedance at WQM station C7 were recorded on 01, 04 and 19 December
2017, 2 limit level turbidity exceedance at WQM station C7 was recorded at WQM station
C7 was recorded on 01 and 16 December 2017 in the December 2017 reporting
period.
1 action level
suspended solid exceedance was recorded at WQM station C7 on 01 December 2017
and 2 limit level suspended solid exceedance were recorded at WQM station C7 on
04 and 16 December 2017 in the December 2017 reporting period.
Diaphragm wall
cutting works and seabed reinstatement works were conducted adjacent to the
monitoring location on 01 December 2017 during monitoring date during flood
tide and ebb tide while silty plume was observed dispersing from the temporary
cut slope through the defective impermeable barrier deployed and affecting the
nearby water quality. Hence, the exceedances recorded were considered as
Project related.
Diaphragm wall
concrete coring works was conducted at TS3 North under Contract HY/2010/08 on
04 December 2017 and mitigation measure including deployment of silt curtain to
enclose the works area and deployment and maintenance of silt screen of
concerned water intake were implemented by the Contractor. No particular water quality
impact from construction works was observed. In view of above, it is considered
that the exceedance was not related to Project works.
Temporary
reclamation removal works was conducted under Contract HY/2010/08 adjacent to
the monitoring station on 16 December 2017 and silty plume originated from
temporary reclamation removal works influencing the water quality of the
waterbody and concerned water intake within the silt curtain enclosed area. Hence,
the exceedances recorded were considered as Project related.
No marine
construction activity was conducted under Contract HY/2010/08 on 19 December
2017 on the monitoring date and the silt screen installed at for concerned
water intake were maintained and generally in order. Hence, it is considered
that the exceedance was not related to Project works.
4.3.18 1 limit level
turbidity exceedance was recorded on at WQM station C7 on 12 January 2018 during
flood tide in the January 2017 reporting period.
No marine
construction activity was conducted under Contract HY/2010/08 on 12 January 2018
and the silt screen installed at for concerned water intake were maintained and
generally in order. Hence, it is considered that the exceedance was not related
to Project works.
4.3.19 1 limit level
turbidity and suspended solids exceedance was recorded on at WQM station C7 on
22 February 2018 during flood tide in the February 2018 reporting period.
No marine
construction activity was conducted under Contract HY/2010/08 on the monitoring
date and the silt screen installed at for concerned water intake were
maintained and generally in order. Hence, it is considered that the exceedance
was not related to Project works.
Table 4.17
Enhance Dissolved Oxygen Monitoring Stations for Contract no. HY/2010/08
Station
Ref. |
Location |
C6 |
Excelsior
Hotel |
C7 |
Windsor House
Cooling |
Remarks:
Enhanced DO
monitoring at Windsor House Cooling (Station Ref: C7) was temporarily suspended
since 22 October 2014 with respect to the formation of temporary reclamation
zone TS3 and was resumed from 1 February 2018 onwards with respect to the
completion of removal of temporary reclamation zone.
4.3.20 No action or limit
level exceedance was recorded at Enhanced DO monitoring station C6 in the
December 2017 reporting period.
4.3.21 No action or limit
level exceedance was recorded at Enhanced DO monitoring station C6 in the
January 2018 reporting period.
4.3.22 No action or limit
level exceedance was recorded at Enhanced DO monitoring stations C6 and C7 in
the February 2018 reporting period.
Contract no. HK/2009/01 - Wan Chai Development
Phase II – Central –Wanchai Bypass at HKCEC
4.4.1 No Inert C&D waste and
non-inert C&D waste was
disposed of for the site works in this reporting period. Details of the waste
flow table are summarized in Table 4.18.
Table 4.18 Details of Waste Disposal for Contract no. HK/2009/01
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
62116.405 |
TKO137, TM38 |
Inert C&D materials recycled, m3 |
NIL |
5856.5 |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
1673.69 |
SENT Landfill |
Non-inert C&D materials recycled, kg |
NIL |
203993 |
N/A |
Chemical waste disposed, kg |
NIL |
10250 |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal)
, m3 |
NIL (Bulk Volume) |
97428.2 (Bulk Volume) |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
NIL (Bulk Volume) |
52250 (Bulk Volume) |
East of Cha Chau |
Dredged Sediment Requiring Type 3 – Special Treatment / Disposal contained in
Geosynthetic Containers |
NIL (Bulk Volume) |
6773 (Bulk Volume) |
East of Cha Chau |
4.4.2 There were no Marine Sediment (Type 1 –
Open Sea Disposal) and no Marine Sediment
(Type 1- Open Sea Disposal (Dedicate Sites) & Type 2- Confined Marine
Disposal) disposed of in this reporting quarter.
Contract no. HK/2009/02 - Wan Chai Development
Phase II – Central – Wan Chai Bypass at WanChai East
4.4.3 No Inert and non-inert C&D waste were disposed of for the
site works in this reporting period. Details of the waste flow table are
summarized in Table 4.19.
Table 4.19 Details of Waste Disposal for Contract no. HK/2009/02
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
276075.1 |
TKO137/ TM 38 |
Inert C&D materials recycled, m3 |
NIL |
18161 |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
1515.103 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
N/A |
N/A |
N/A |
Chemical waste disposed, kg |
NIL |
13860 |
SENT Landfill |
Marine Sediment (Type 1 – Open Sea
Disposal), m3 |
NIL |
240222 (Bulk volume) |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal), m3 * |
NIL |
146445 (Bulk volume) |
East of Sha Chau |
4.4.4 There was no Marine Sediment (Type 1 –
Open Sea Disposal) and no Marine
Sediment (Type 1- Open Sea Disposal (Dedicate Sites) & Type 2- Confined
Marine Disposal) disposed of in this reporting quarter.
Contract no. HY/2009/15 -
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)
4.4.5 There was no Inert C&D waste disposed in this
reporting period and no non-inert C&D waste was disposed in this reporting
period. Details of the waste flow table are summarized in Table 4.20.
Table 4.20 Details of Waste Disposal for Contract no. HY/2009/15
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Remarks |
Inert C&D materials disposed, m3 |
NIL |
141579.2 |
Tuen Mun Area 38 |
NIL |
NIL |
65216 |
TKO137 FB |
NIL |
|
Inert C&D materials recycled, m3 |
NIL |
8127.21 |
HY/2010/08 |
NIL |
NIL |
304 |
Ex-PCWA |
NIL |
|
NIL |
111.9 |
TS4 |
NIL |
|
Non-inert C&D materials disposed, m3 |
NIL |
252.2 |
SENT Landfill |
NIL |
Non-inert C&D materials recycled, kg |
NIL |
299361.5 |
N/A |
NIL |
Chemical waste disposed, kg |
NIL |
8,200 |
N/A |
NIL |
Marine Sediment (Type 1 – Open Sea Disposal)
, m3 |
NIL |
156909 (Bulk Volume) |
South of Cheung Chau |
Dredging from TCBR1E /
TCBR1W / TCBR2/ TCBR3 / TCBR4 / Maintenance dredging |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
NIL |
327746 (Bulk Volume) |
East of Sha Chau |
Dredging from TCBR1E /
TCBR1W / TCBR2/ TCBR3 / TCBR4 / Maintenance dredging |
Marine Sediment (Type 3 – Special Treatment
/ Disposal contained in Geosynthetic Containers) |
NIL |
12640 (Bulk Volume) |
East of Sha Chau |
Dredging from TCBR1W /
Maintenance dredging |
Marine Sediment (Type 2 – Confined Marine
Disposal), m3 |
NIL (Bulk Volume) |
9350 (Bulk Volume) |
East of Sha Chau |
Dredging from Eastern
Breakwater of CBTS |
Marine Sediment (Type 1 – Open Sea Disposal)
, m3 |
NIL (Bulk Volume) |
600 (Bulk Volume) |
East Sha Chau / South
of The Brothers |
Dredging from Phase 3
Mooring Re-arrangement |
Marine Sediment (Type 2– Confined Marine Disposal)
, m3 |
NIL (Bulk Volume) |
14,780 (Bulk Volume) |
South of The Brothers |
Dredging from Phase 3
Mooring Re-arrangement |
Marine Sediment (Type 3 – Special Treatment
/ Disposal contained in Geosynehetic Containers) , m3 |
NIL (Bulk Volume) |
2,760 (Bulk Volume) |
South of The Brothers |
Dredging from Phase 3
Mooring Re-arrangement |
4.4.6 There were no marine sediments Type1- Open Sea
Disposal and no Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 –
Confined Marine Disposal in this reporting quarter.
Contract
no. HY/2009/19 – Central- WanChai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link
4.4.7 No Inert and non-inert C&D waste were disposed
of in this reporting quarter. Details of the waste flow table are summarized in
Table 4.21.
Table
4.21 Details of Waste Disposal for Contract no. HY/2009/19
Waste Type |
Quantity this quarter |
Cumulative
Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
355921.04 |
TM38 |
Inert C&D materials
recycled, m3 |
NIL |
59367 |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
1068.6 |
N/A |
Non-inert C&D materials recycled, kg |
NIL |
333.14 |
N/A |
Chemical waste disposed, L |
NIL |
2.12 |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal), m3 |
NIL |
162 |
South Cheung Chau |
Marine Sediment (Type 2 – Confined Marine Disposal) , m3 |
NIL |
681 |
East Sha Chau |
Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) &
Type 2 – Confined Marine Disposal) , m3 |
NIL |
4976.00 |
N/A |
4.4.8 There were no marine sediments Type1- Open Sea
Disposal and no Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 –
Confined Marine Disposal in this reporting quarter.
Contract
no. HK/2012/08 –Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan
Chai West
4.4.9 No Inert and non-inert C&D waste were disposed
of in this reporting quarter. Details of the waste flow table are summarized in
Table 4.22.
Table
4.22 Details of Waste Disposal for Contract no. HK/2012/08
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL NIL |
4131 273 |
TM38 TKO 137 |
Inert C&D materials recycled, m3 |
NIL |
NIL |
NIL |
Non-inert C&D materials disposed, m3 * |
NIL |
400 |
SENT |
Non-inert C&D materials recycled, kg |
NIL |
NIL |
N/A |
Chemical waste disposed, L |
NIL |
NIL |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal),
m3 * |
NIL (Bulk volume) |
31759 (Bulk volume) |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) &
Type 2 – Confined Marine Disposal) , m3 * |
NIL (Bulk volume) |
108542 (Bulk volume) |
South of The Brothers (from 27 Aug 2013 onwards) |
*Remarks: The details of waste disposal is recorded in calendar month
period.
4.4.10 No Marine Sediment Type 1 – Open Sea
Disposal (Delicate Sites) & Type 2 – Confined Marine Disposal and Marine
Sediment Type 1 – Open Sea Disposal disposed in this reporting quarter.
Contract
no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8)
4.4.11 Inert C&D waste was disposed in this
reporting month, while no non-inert C&D waste disposed in this reporting period. Details of the waste flow table are summarized in Table
4.23
Table 4.23 Details of Waste Disposal for Contract no. HY/2010/08
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
1000.778 NIL |
92433.315 19739.4 |
TM38 TKO137 |
Inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled, kg |
NIL |
NIL |
N/A |
Chemical waste disposed, L |
NIL |
NIL |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal) |
NIL |
62559.4 |
South Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type
2 – Confined Marine disposal) |
NIL |
28309.2 |
Brothers Island |
Marine Sediment (Type 3 – Special Treatment) |
NIL |
7780 |
Brothers Island |
4.4.12 There were no Type 1 – Open Sea Disposal
and no Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined
Marine Disposal disposed in this reporting month, and no Type 3- Special
Treatment disposed in this reporting quarter.
5.0.1. The Event Action Plan for construction noise, air
quality and water quality are presented in Appendix 5.1.
Reporting period of December 2017
5.1.1 Two limit level
exceedances were recorded at M1a – Footbridge for Harbour Road Sports Centre on
04 and 11 December 2017 and the exceedances were concluded as non-Project related.
5.1.2 Two limit level
exceedances were recorded at M6 – HK Baptist Church Henrietta Secondary School
on 08 and 20 December 2017 and the limit level exceedance recorded on 08 was concluded
as non-Project related.
The limit level exceedance recorded at M6 on 20
December 2017 was concluded as related to the breaking works under Contract
HY/2009/19 and remedial actions were implemented by the Contractor accordingly
and no further exceedance was recorded.
Reporting period of January 2018
5.1.3 Three limit level
exceedances were recorded at M1a – Footbridge for Harbour Road Sports Centre on
29 December 2017, 16 and 23 January 2018 in the reporting month. After the investigation,
the exceedances were concluded as non-project related.
Reporting period of February 2018
5.1.4 One limit level
exceedances were recorded at M1a – Footbridge for Harbour Road Sports Centre on
2 February 2018 in the reporting month. After the investigation, the exceedance
was concluded as non-project related.
Reporting period of December 2017
5.2.1 One 24hr TSP action level exceedance and one 1hr TSP limit level
exceedance were recorded at CMA5b – Pedestrian Plaza on 11 and 12 December 2017
respectively. One 1hr TSP action level exceedance was recorded at CMA5b –
Pedestrian Plaza on 23 December 2017. The exceedances were concluded not
related to the Project works under Contract HK/2012/08.
Reporting period of January 2018
5.2.2 One 24hr TSP action level exceedance was recorded at CMA5b –
Pedestrian Plaza on 29 December 2017 in the reporting month. After the
investigation, the exceedance was concluded as not related to the Project works
under Contract HK/2012/08.
Reporting period of February 2018
5.2.3 No action or limit level exceedance was recorded in the February
2018 reporting period.
Reporting
period of December 2017
5.3.1
5 action level turbidity exceedances were recorded at WQM station WSD19
on 27 November 2017, 01, 09, 12 and 23 December 2017 and 7 limit level
turbidity exceedances were recorded at WQM station WSD19 on 29 November, 01,
04, 09, 14, 19 and 21 December 2017 and the exceedances were considered as not
related to the Project.
1 limit level suspended solid exceedance
was recorded at WQM station WSD19 on 29 November 2017 and the exceedances were
considered as not related to the Project.
5.3.2
1 limit level turbidity exceedance was recorded at WQM station C1 on 19
December 2017 and the exceedances were concluded as not related to the Project.
5.3.3
1 action level turbidity exceedances were recorded at WQM station P1 on
21 December 2017 and 1 limit level turbidity exceedance was recorded at WQM
station P1 on 19 December 2017 and the exceedances were considered as not
related to the Project.
5.3.4
1 limit level turbidity exceedance was recorded at WQM station P3 on 19
December 2017 and the exceedances were considered as not related to the
Project.
5.3.5
1 limit level turbidity exceedance was recorded at WQM station P4 on 19
December 2017 and the exceedances were considered as not related to the
Project.
5.3.6
2 action level turbidity exceedance were recorded at WQM station
RW21-P789 on 01 and 21 December 2017 and 3 limit level turbidity exceedances
were recorded at RW21-P789 04, 19 and 23 December 2017 and the exceedances were
concluded as not related to the Project.
5.3.7
3 action level turbidity exceedance at WQM station C7 were recorded on
01, 04 and 19 December 2017. 2 limit level turbidity exceedance at WQM station
C7 was recorded at WQM station C7 was recorded on 01 and 16 December 2017. The
exceedances recorded on 04 and 19 December were concluded as non-Project
related.
1 action level suspended solid
exceedance was recorded at WQM station C7 on 01 December 2017 and 2 limit level
suspended solid exceedance were recorded at WQM station C7 on 04 and 16
December2017. The exceedance recorded on 04 December 2017 was concluded as non-Project
related.
The exceedances on 01 and 16 December
2017 were concluded as related to the Project works under Contract HY/2010/08.
Remedial actions were implemented by the Contractor of HY/2010/08 according to
the Event and Action Plan.
Reporting
period of January 2018
5.3.8
Based on Contractor confirmed site information on no marine construction
activities on 01 January 2018, the respective scheduled water quality
monitoring event at all WQM stations and enhanced DO monitoring was temporary
suspended on 01 January 2018 during ebb tide and flood tide accordingly.
5.3.9
4 action level turbidity exceedance was recorded at WSD19 on 28 December
2017, 30 December 2017, 8 January 2018 and 23 January 2018 during flood tide in
the reporting month. After the investigation, the exceedances were concluded as
non-project related.
5.3.10
1 action level turbidity exceedance and 1 limit level turbidity
exceedance were recorded at WQM station RW21-P789 on 28 December 2017 and 8
January 2018 during flood tide in the reporting month. After the investigation,
the exceedances were concluded as non-project related.
5.3.11
1 limit level turbidity exceedance was recorded on at WQM station C7 on
12 January 2018 during flood tide in the reporting month. After the
investigation, the exceedance was concluded as non-project related.
Reporting
period of February 2018
5.3.12
Due to temporarily site closure and road closure around the SCL project
site on 27 January 2018 with respect to the explosive discovery at the
aforementioned construction site, the scheduled water quality monitoring event
at WQM station RW21-P789 on 27 January 2018 during flood tide and ebb tide were
cancelled.
5.3.13
Based on Contractor confirmed site information on no marine construction
activities on 17 February 2018, the respective scheduled water quality
monitoring event at all WQM stations and Enhanced DO monitoring station was
temporary suspended on 17 February 2018 during ebb tide and flood tide
accordingly.
5.3.14
With respect to the completion of the removal of the temporary
reclamation at TS3, the suspended Enhance DO monitoring C7 would be resumed at
the previous location from 01 February 2018 onwards.
5.3.15
1 limit level turbidity and suspended solids exceedance was recorded on
at WQM station C7 on 22 February 2018 during flood tide in the reporting month.
After the investigation, the exceedance was concluded as non-project related.
5.4.1
There was no non-compliance from the site audits in the reporting
period. During environmental site inspections conducted during the reporting
period, minor deficiencies were noted.
Reporting
period of December 2017
5.5.1
Project related exceedances were recorded at WQM station C7 on 01 and 16
December 2017.
Diaphragm wall cutting works and seabed
reinstatement works were conducted adjacent to the monitoring location on 01
December 2017 during flood tide and ebb tide while silty plume was observed
dispersing from the temporary cut slope through the defective impermeable
barrier deployed and affecting the nearby water quality. Hence, the exceedance
recorded were considered as Project related.
Temporary reclamation removal works was
conducted under Contract HY/2010/08 adjacent to the monitoring station on 16
December 2017 and silty plume originated from temporary reclamation removal
works influencing the water quality of the waterbody and concerned water intake
within the silt curtain enclosed area. . Hence, the exceedance recorded was
considered as Project related.
5.5.2
Project related noise exceedance was recorded at NM station M6 - HK Baptist
Church Henrietta Secondary School on 20 December 2017.
Breaking of paving surface at Pier F5
and F6 under Contract HY/2009/19 was conducted during the measurement on 20
December 2017 and breaking operation behind the IECL noise enclosure was observed
as the major noise influence during measurement. Hence, the exceedance was
considered as Project related.
Reporting period of January 2018
5.5.3
There was no non-compliance from the site audits in the January 2018
reporting period.
Reporting period
of February 2018
5.5.4 There was no non-compliance from the site audits in
the February 2018 reporting period.
Reporting
period of December 2017
5.6.1
With respect to the project related exceedances recorded at WQM station
C7 on 01 December 2017, upon identification of defects observed on 01 December
2017 during ebb tide, rectification measure including rectification of
impermeable barrier deployed around temporary cut slope was implemented by the
Contractor on 01 December 2017 flood tide. Subsequently rectification measures
including i) rectification of silt curtain and impermeable barrier deployed around
diaphragm wall cutting works and ii) cleaning of water holding tank were
implemented by the Contractor by 02 December 2017. Additional monitoring in
accordance with the Event and Action Plan was conducted on 02 December 2017 and
no further turbidity exceedance was recorded.
5.6.2
With respect to the project related exceedances recorded at WQM station
C7 on 16 December 2017 during flood tide, upon identification of the
exceedance, tidying of silt screen and additional silt curtain around the
concerned water cooling water intake were implemented by the Contractor of
HY/2010/08 and flushing of the water holding tank was also implemented. Subsequent
monitoring was conducted on 17 December 2017 during ebb tide at 0225hrs and no
further exceedance was recorded. In addition, the Contractor of HY/2010/08 was
also advised to rectify the gap opening at the ends of the outer perimeter silt
curtain deployed to enclose the works front to avoid adverse water quality
impact to the CBTS area. The Contractor of HY/2010/08 was also advised to review
the use of impermeable barrier to separate the sheet piling works area and the concerned
water intake without blocking the water circulation to the water intake to
safeguard the water intake.
5.6.3
With respect to the noise exceedance recorded at NM station M6 on 21
December 2017, upon identification of the noise concern, the Contractor was
immediately notified of the observation In view of subsequent monitoring date
with respect to the completion of school examination, no further exceedance was
recorded during additional monitoring conducted on 21 December 2017 at the
concerned location, no further adverse impact was considered. Nevertheless, the
Contractor of HY/2009/19 was advised to adopt additional noise mitigation
measure for future breaking works, if any, at the concerned location during
examination period, such as provision of localized movable noise barrier to
ensure that the nearby noise sensitive receiver would not be adversely
affected.
Reporting
period of January 2018
5.6.4
There was no particular action taken since no non-compliance was
recorded from the site audits in the January 2018 reporting period.
Reporting period of February 2018
5.6.5
There was no particular action taken since no non-compliance was
recorded from the site audits in the February 2018 reporting period.
6.0.1. No environmental complaint was received
in the December 2017, January 2018 and February 2018 reporting period. .
6.0.2.
The details of cumulative complaint
log and summary of complaints are presented in Appendix
6.1.
6.0.3. Cumulative statistic on complaints and successful
prosecutions are summarized in Table 6.1 and Table 6.2 respectively.
Table 6.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement works
(Mar 2010) to last reporting quarter |
47 |
December 2017 – February 2018 |
0 |
Project-to-Date |
47 |
Table 6.2 Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this quarter (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.1. According
to Condition 3.4 of the EP-356/2009, this section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III, Central-Wanchai Bypass
and Island Eastern Corridor Link projects.
7.0.2. According
to the Final EM&A Report of Central Reclamation Phase III (CRIII) for
Contract HK 12/02, the major construction activities were completed by end of
January 2014 and no construction activities were undertaken thereafter and the
water quality monitoring was completed in October 2011 and no Project-related exceedance
was recorded for air and noise monitoring.
It can be concluded that cumulative construction impact due to the
concurrent activities of the current projects with the Central Reclamation
Phase III (CRIII) was insignificant.
7.0.3.
According to the construction programme of Central-Wanchai Bypass at
Wanchai West at the Central Reclamation Phase III area roadworks, back-filling,
reinstatement of culvert K, drainage and trimming of rock level were performed
in February 2018 reporting month.. As no
project related exceedance were recorded during the reporting period,
cumulative construction impact due to the concurrent activities of the current
projects with the Central Reclamation Phase III (CRIII) was considered as
insignificant.
7.0.4. According to the construction programme of Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects, the major construction activities under Wan Chai Development Phase II
were road and drains construction and removal of preparation of temporary
reclamation at Wan Chai West and Wan Chai East. The major construction
activities under Central-Wan Chai Bypass and Island Eastern Corridor Link Projects
were drainage works and ventilation building construction at Central;
reinstatement works at Causeway Bay, road works at Victoria Park; bridge
construction, approach ramp construction and building construction at North
Point area in the reporting period. In addition, other non-Wan Chai Development
Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects was
observed undertaken at Wan Chai North and North Point area.
7.0.5. No significant air impact from
construction activities was anticipated in the reporting month. Besides, no
project related exceedance was recorded during the air and noise environmental
monitoring events in the reporting month. Thus, it is evaluated that the
cumulative construction impact from the concurrent projects including Central
Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII),
Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) was
insignificant.
8.0.1. The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
8.0.2.
Project related exceedances were recorded at WQM station C7 on 01 and 16
December 2017 in the December 2017 reporting period.
Diaphragm wall cutting works and seabed
reinstatement works were conducted adjacent to the monitoring location On 01
December 2017 during flood tide and ebb tide while silty plume was observed
dispersing from the temporary cut slope through the defective impermeable
barrier deployed and affecting the nearby water quality. Hence, the exceedance
recorded were considered as Project related.
Temporary reclamation removal works was
conducted under Contract HY/2010/08 adjacent to the monitoring station on 16
December 2017 and silty plume originated from temporary reclamation removal
works influencing the water quality of the waterbody and concerned water intake
within the silt curtain enclosed area. . Hence, the exceedance recorded was
considered as Project related.
8.0.3.
Project related noise exceedance was recorded at NM station M6 - HK
Baptist Church Henrietta Secondary School on 20 December 2017 in the December
2017 reporting period.
Breaking of paving surface at Pier F5
and F6 under Contract HY/2009/19 was conducted during the measurement on 20
December 2017 and breaking operation behind the IECL noise enclosure was
observed as the major noise influence during measurement. Hence, the exceedance
was considered as Project related.
8.0.4.
There was no non-compliance from the site audits in the January 2018 and
February 2018 reporting period.
8.0.5.
No environmental complaint was received in the December 2017, January
2018 and February 2018 reporting period. .
8.0.6.
No summon or prosecution was received in the December 2017, January 2018
and February 2018 reporting period.
8.0.7. The construction programmes
of individual contracts are provided in Appendix 8.1.